High-End House Renovation Company Building Contractors London

Dominant Construction’s team has been delivering successful projects for clients across Hammersmith and central London in areas such as: Chelsea, Kensington, Belgravia, Richmond, Fulham, Ealing, and Twickenham for the past fifteen years. Transforming homes into modern masterpieces is our passion. From the finest materials and cutting-edge technologies to our focus on exceptional design, we aim to exceed expectations at every step.

Our commitment to outstanding customer service drives transparency and honesty across all aspects of our work. At Dominant Construction, we are committed to delivering projects that meet our clients' needs, with a focus on attention to detail, timeliness, and value.
Find out more

CONCEPT TO COMPLETION

Our diverse team brings together a wide range of specialist skills in interiors, architecture, and construction, delivering an exceptional portfolio of projects.
Learn more
Learn more
Learn more
Latin dance classes In manhattan

Trusted Builders in
Fulham and Hammersmith

Dominant Construction, your trusted local builders located at 185 Fulham Palace Road, London W6, proudly serving Fulham, Hammersmith, and West London. For years, we’ve helped homeowners transform their spaces with high-end home renovations, loft conversions, basement conversions, and house extensions - all customised to fit your needs, budget, and timeline.

Whether you're looking to extend your home for extra space, transform an unused loft into a modern living area, or renovate your property, our experienced team is committed to making the entire process seamless, professional, and hassle-free.

At Dominant Construction, we’re recognised for our energy, transparency, and honesty in every project. We take pride in our careful attention to detail, delivering on time, and offering outstanding value, because your vision deserves nothing less than the finest craftsmanship.

If you are looking for reliable builders near Fulham or Hammersmith, we are here to help. Get in touch today, and let us begin creating your dream space.
Find out more

RECENT PROJECTS

  • VIEW PROJECT
  • VIEW PROJECT
  • VIEW PROJECT
  • VIEW PROJECT
OUR BLOG
    Reliable Builders in Fulham & Hammersmith – Expert Renovations, Loft Conversions & House Extensions
    Blog

    Full House Renovation Cost London 2026: Budget, Timeline & What to Expect

    Quick Answer

    A full house renovation in London in 2026 can cost roughly £100,000–£350,000+ for a typical 3–4 bedroom property, depending on size, structural work, services and specification. Current London market benchmarks broadly sit around £800–£1,950+ per m², with premium period properties potentially higher. Allow a contingency and define the scope before comparing renovation quotations.

    How Much Does a Full House Renovation Cost in London in 2026?

    There is no single London renovation price.
    A property that needs a new kitchen, bathrooms, decoration and flooring is a very different project from a Victorian house being stripped back, structurally altered and completely rewired and replumbed.
    As a broad 2026 market guide, whole-house renovation can fall somewhere around £800–£1,950+ per m², depending on specification, structural work, services, property condition and site constraints.
    A typical three-bedroom refurbishment may sit around £100,000–£180,000, while substantial structural renovations can move towards £200,000–£350,000+.
    These figures are useful for establishing an initial budget, but they should not be treated as a quotation.

    A useful starting budget

    Project typeIndicative 2026 London budget
    Light refurbishment
    £45,000–£90,000+
    Full 3-bedroom refurbishment
    £100,000–£180,000
    Substantial whole-house renovation
    £150,000–£250,000+
    Structural / high-spec renovation
    £200,000–£350,000+
    Large premium period property
    £350,000+
    The scope behind the figure matters more than the figure itself.
    A £150,000 quotation can represent excellent value on one property and be completely unrealistic on another.

    What Actually Counts as a Full House Renovation?

    This is where renovation budgets often become confusing.
    A light refurbishment might involve:
    • redecorating
    • replacing flooring
    • upgrading a kitchen
    • refurbishing bathrooms
    • replacing selected fittings
    • minor electrical work
    A genuine whole-house renovation can involve considerably more:
    • complete strip-out
    • new electrical installation
    • new plumbing
    • heating replacement
    • structural alterations
    • new internal layouts
    • RSJs and structural steel
    • new bathrooms
    • new kitchen
    • replastering
    • insulation upgrades
    • new flooring
    • bespoke joinery
    • doors
    • decoration
    • external repairs
    • roof works
    • drainage
    • Building Regulations compliance
    That difference explains why homeowners can receive quotations that appear dramatically different for "the same" renovation.
    They usually aren't the same project.

    London Renovation Cost Per m² in 2026

    Using a price per square metre is useful for creating an initial budget, but it should never replace a proper survey and specification.
    A lower-spec refurbishment may sit towards the bottom of the range, while a period property involving structural alterations, bespoke joinery, premium kitchens, multiple bathrooms and upgraded services can move substantially higher.
    For example, a 150m² house at £1,500 per m² would imply approximately £225,000.
    But that calculation does not tell you whether the property actually needs £1,500 per m² worth of work.
    It is a starting point, not a quotation.

    What Makes a London Renovation Expensive?

    1. Structural Alterations

    Moving walls can completely change the construction scope.
    A simple non-structural partition is one thing.
    Removing a load-bearing wall and creating a wide opening between rooms may require:
    • structural engineer calculations
    • temporary works
    • steel beams
    • padstones
    • fire protection
    • Building Regulations approval
    • making good and replastering
    An RSJ itself is only part of the cost.
    The labour, temporary support, installation, fire protection and associated finishes all need to be considered.

    2. Rewiring the House

    Older London properties often require substantially more electrical work than a cosmetic renovation suggests.
    A full rewire can involve:
    • new consumer unit
    • new circuits
    • sockets
    • lighting
    • data cabling
    • kitchen supplies
    • bathroom electrical requirements
    • external lighting
    • smoke and heat detection
    • testing and certification
    If walls and ceilings are already being opened, this is often the logical time to deal with outdated services.

    3. Plumbing and Heating

    Replacing old plumbing can be one of the less visible but more important parts of a renovation.
    A substantial project may involve:
    • new hot and cold-water pipework
    • new soil and waste connections
    • new radiators
    • new heating controls
    • hot-water cylinder
    • boiler replacement
    • underfloor heating
    • upgraded insulation around services
    The heating strategy should be decided early rather than after the floors and walls have been finished.

    4. Energy Efficiency Is Now a Bigger Part of Renovation Planning

    Energy performance deserves serious consideration during a major renovation.
    Depending on the property and scope of work, this may involve:
    • roof insulation
    • wall insulation
    • floor insulation
    • draught reduction
    • glazing improvements
    • heating controls
    • heat-loss reduction
    • hot-water efficiency
    • ventilation
    However, period properties require care.
    A Victorian solid-wall house should not simply be treated like a modern cavity-wall building.
    Insulation, ventilation and moisture movement need to be considered together. The wrong retrofit detail can create problems rather than solve them.

    5. Kitchens and Bathrooms

    The kitchen and bathrooms can consume a substantial part of a renovation budget.
    There is an enormous difference between:
    Standard refurbishment
    and
    Fully bespoke installation
    The budget can change according to:
    • cabinetry
    • stone worktops
    • appliances
    • sanitaryware
    • brassware
    • lighting
    • tiling
    • joinery
    • mirrors
    • underfloor heating
    • extraction
    • specialist finishes
    A bathroom is not simply the cost of the bath, basin and toilet.
    Behind the finished surfaces are waterproofing, plumbing, ventilation, electrical work, substrates, tiling and specialist installation.

    Victorian House Renovation Costs Can Be Different

    London has a huge amount of Victorian housing stock, and these properties often make excellent renovation projects.
    But they can also contain surprises.
    Typical issues can include:
    • uneven floors
    • outdated wiring
    • old plumbing
    • inadequate insulation
    • chimney breasts
    • timber decay
    • roof problems
    • movement
    • poorly executed previous alterations
    • damp associated with inappropriate modern materials
    • limited access
    • party wall considerations
    The architectural character can also influence the specification.
    Original cornices, fireplaces, doors, staircases and timber floors may be worth retaining rather than replacing.
    The objective is not necessarily to make everything new.
    It is to decide what should be retained, what should be repaired and what genuinely needs replacing.

    Should You Renovate or Extend at the Same Time?

    This is an important question.
    If the property already needs a complete renovation, it can make sense to consider an extension during the same project.
    For example:
    Existing house
    → complete renovation
    → new services
    → new kitchen
    → rear extension
    → new flooring
    → decoration
    rather than:
    Year 1: renovate
    Year 2: extension
    Year 3: repair the finishes disturbed by the extension
    Combining projects does not automatically make the work cheaper, but it can make logistical and construction planning more efficient.
    It can also allow structural, service and finishing work to be coordinated instead of disturbing completed rooms later.
    See our extension services for more information about residential extension projects.

    How Long Does a Full House Renovation Take?

    A realistic timeline depends heavily on the scope.
    For a substantial London renovation, several months is normal, with more complex projects taking considerably longer.
    A typical sequence might look like:

    Stage 1 — Survey and design

    2–8+ weeks
    Depending on whether architectural, structural and planning work is required.

    Stage 2 — Pre-construction

    Several weeks
    Final specifications, procurement, contracts, statutory approvals and programme planning.

    Stage 3 — Strip-out and enabling works

    2–4 weeks
    Removal of existing kitchens, bathrooms, finishes, redundant services and selected walls.

    Stage 4 — Structural and first-fix works

    4–10+ weeks
    This can include steelwork, structural alterations, plumbing, electrical work, heating, insulation and new partitions.

    Stage 5 — Plastering and second fix

    4–8 weeks
    Walls, ceilings, joinery, sockets, lighting, doors and other finishes begin to come together.

    Stage 6 — Kitchens, bathrooms and final finishes

    4–8+ weeks
    Installation, tiling, flooring, decoration, sanitaryware, appliances and final joinery.
    A complex whole-house renovation can therefore run for many months rather than weeks.
    The programme should be established from the actual scope rather than promising an attractive but unrealistic completion date.

    What About Planning Permission?

    Not every renovation requires planning permission.
    Many purely internal alterations may not require a planning application, but extensions and certain external alterations can.
    The situation becomes more sensitive for:
    • listed buildings
    • conservation areas
    • properties with Article 4 restrictions
    • significant external alterations
    • extensions
    • roof alterations
    • changes affecting historic features
    Before starting a major renovation, establish the property's planning position.
    This is particularly important in London, where period housing and conservation areas are common.

    Building Regulations Are Not the Same as Planning Permission

    This distinction is important.
    You can have work that does not need planning permission but still needs to comply with Building Regulations.
    Structural alterations are a good example.
    So are many works involving:
    • structural elements
    • electrical installations
    • insulation
    • thermal elements
    • fire safety
    • drainage
    • ventilation
    • windows
    • heating
    Planning permission and Building Regulations address different aspects of construction.
    A renovation should be assessed against both.

    What About Listed and Period Properties?

    This deserves its own conversation.
    London has an enormous number of period homes, conservation areas and listed properties.
    The challenge is balancing:
    heritage
    with
    modern living
    and
    technical performance.
    Original architectural features can sometimes be the most valuable part of the building.
    That could mean restoring:
    • fireplaces
    • cornices
    • ceiling roses
    • timber doors
    • staircases
    • sash windows
    • original flooring
    • period joinery
    while introducing contemporary elements elsewhere.
    The result does not need to look like a museum.
    A well-executed renovation can retain the character of the original building while making the house work properly for modern life.

    The Hidden Costs Homeowners Often Forget

    The construction quotation is not always the entire project budget.
    Allow for items such as:

    Professional fees

    Potentially including:
    • architect
    • structural engineer
    • planning consultant
    • party wall surveyor
    • building control
    • specialist consultants

    Site logistics

    Particularly in London:
    • scaffolding
    • hoarding
    • skips
    • waste removal
    • parking arrangements
    • material deliveries
    • restricted access

    Temporary accommodation

    If the entire house is being renovated, living elsewhere may become necessary.

    Contingency

    Existing buildings contain unknowns.
    Once walls and floors are opened, you may discover:
    • damaged timbers
    • inadequate drainage
    • unexpected structural conditions
    • obsolete services
    • previous alterations
    • hidden water damage
    A contingency is therefore not wasted money.
    It is protection against the building telling you something you couldn't see during the initial survey.

    How Much Contingency Should You Allow?

    There is no universal percentage that works for every project.
    A relatively well-understood property with detailed surveys and drawings may require less contingency than an old house with significant unknowns.
    For a substantial renovation, it is sensible to establish a realistic contingency allowance before signing the construction contract.
    The more uncertain the existing building, the more important this becomes.

    How to Compare Renovation Quotes Properly

    Do not simply choose the lowest number.
    Ask whether each quotation includes the same scope.
    Compare:
    • strip-out
    • structural work
    • steel
    • plumbing
    • electrical
    • heating
    • insulation
    • plastering
    • flooring
    • kitchen
    • bathrooms
    • joinery
    • decoration
    • external works
    • waste
    • scaffolding
    • preliminaries
    • Building Regulations
    • exclusions
    • VAT
    A £120,000 quotation and a £180,000 quotation may look very different until you discover that one excludes the kitchen, bathrooms, flooring and decoration.
    That is not a £60,000 saving.
    It is simply a different quotation.

    The Best Way to Control a Renovation Budget

    The earlier the specification is fixed, the easier the budget becomes to manage.
    Before construction begins, try to establish:

    1. What is structurally changing?

    Walls, openings, floors, roof and steelwork.

    2. What services are being replaced?

    Electrical, plumbing, heating, ventilation and drainage.

    3. What is being retained?

    Original floors, fireplaces, doors, cornices, staircases and other period features.

    4. What is the specification?

    Kitchen, bathrooms, flooring, sanitaryware, lighting, joinery and decoration.

    5. What is excluded?

    This is just as important as what is included.

    6. What is the contingency?

    Have an agreed reserve for unknown conditions.
    This gives you a much clearer basis for comparing contractors.

    Why a Detailed Survey Matters Before You Price the Work

    The most useful renovation quotation starts with understanding the building.
    A proper pre-construction assessment should consider:
    • existing structure
    • floor levels
    • roof condition
    • drainage
    • damp
    • electrical installation
    • plumbing
    • heating
    • insulation
    • windows
    • access
    • party wall implications
    • planning restrictions
    • listed status
    • conservation-area considerations
    This is particularly important with older London houses.
    The photograph may show a beautiful period façade.
    It tells you very little about what is happening behind it.

    A Renovation Is Not Just a Collection of Rooms

    A whole-house renovation should be treated as one coordinated construction project.
    Changing the kitchen affects plumbing.
    Changing the layout affects structure.
    Changing the floor affects levels.
    Changing the insulation affects detailing.
    Changing heating affects services.
    That is why design, engineering and construction need to be coordinated before the final finishes are selected.
    You can learn more about our design and build services.

    Is 2026 a Good Time to Renovate a London Property?

    For homeowners who already own the right property, the question is less about finding a universally "cheap" moment to build and more about whether the property justifies the work and whether the project is properly scoped.
    London construction pricing remains highly dependent on labour, specification, site access and the amount of structural and services work involved.
    There is also a practical reason to consider energy performance during a major renovation.
    If walls, roofs, floors, heating and services are already being opened up, some improvements can be much easier to incorporate at that stage than as a separate project later.

    When a Whole-House Renovation Makes Sense

    A complete renovation can be appropriate when:
    • the property has good underlying structure
    • the location works for you
    • the layout is outdated
    • services are approaching the end of their useful life
    • the kitchen and bathrooms need replacement
    • insulation needs improvement
    • several rooms require work simultaneously
    • you want to retain the existing building rather than move
    It can be particularly compelling when the house has strong period character but poor internal functionality.
    You don't have to choose between preserving the building and making it work properly.
    With the right specification, you can do both.

    When You Should Be More Cautious

    A renovation needs careful financial assessment where:
    • the property has significant structural movement
    • drainage is fundamentally defective
    • the roof requires major reconstruction
    • extensive underpinning may be required
    • planning restrictions limit the intended changes
    • the required specification exceeds the property's realistic value
    • the project budget has no contingency
    A detailed survey before committing to construction can save considerably more than it costs.

    Frequently Asked Questions

    How much does a full house renovation cost in London in 2026?

    A full-house renovation can range broadly from around £100,000 to £350,000+, depending on property size, condition, structural work, services, specification and access. Larger or particularly complex period properties can exceed this range.

    How long does a full house renovation take?

    A substantial whole-house renovation commonly takes several months. The programme depends on the size of the property, structural alterations, service replacement, planning requirements, procurement and specification.

    Does a full house renovation need planning permission?

    Not necessarily. Many internal alterations may not require planning permission, but extensions and certain external alterations can. Listed buildings and properties subject to additional planning controls require particular care.

    Do I need Building Regulations approval for a renovation?

    Building Regulations can apply even where planning permission is not required. Structural alterations, thermal upgrades and various building-service works may require approval or certification.

    How much contingency should I allow for a London renovation?

    There is no single percentage suitable for every property. A detailed survey and defined specification can reduce uncertainty, while older properties with unknown structural or service conditions justify a more cautious contingency.

    Is it worth renovating a Victorian house?

    It can be, particularly when the property has strong existing character but requires modernisation. The key is understanding the condition of the structure and services before setting the final budget.

    Should I renovate and extend at the same time?

    If both are already part of the long-term plan, combining them can make logistical and construction sense. It allows structural, service and finishing work to be coordinated rather than disturbing completed rooms later.

    Planning a Full House Renovation in London?

    The most expensive mistake is often not choosing the wrong tile.
    It is starting construction before the scope, structure, services and budget are properly understood.